HealthMED Inc.
"Where health, medicine, and technology meet to fight disease through organized data."
Case Study
Role
Product Operations Associate
Teams
-
Implementation
-
Account Management
-
Support
Problem
Product release of new EMR patient portal
-
MVP expected mid-November 2018
- Due in 100 client offices by January 2019
- Internal and External training required
- Holidays mean fewer working days
Proposed Solution
Agile method for rollout
-
Two-Week Sprints
-
Regular 15-20 min scrums
Planned Training Resources
-
Online FAQ
-
Strategic Email campaign
-
Print Resources
Start
Week 1
November 13 - 16
4 days
- Research - Explore MVP
- Present product to all teams
- Celebrate major milestone!
- Share tasklist (backlog) for sprint
-
volunteers from each team
-
create tester account s
- self-navigate materials
- create GIFs(screentogif.com)
- take notes, provide feedback
- draft mock press release
- create GANTT chart
-
- Gather Feedback for Developers/Engineers
- prioritize into actionable insights for usability
- Run fivesecondtests
Week 2
November 19-21
3 days
-
Create Online Resource
-
gather all materials from last week to develop FAQ
-
outline web source with images and GIFs
-
-
Emails
-
Internal Training Introduction
-
External Product Introduction
-
-
-
-
Finalize and share.
happy thanksgiving!
Week 3
November 26-30
5 days
-
Internal Training Presentation for Support Team
-
Prepare easy printables for practices to share with patients
-
landing page
-
account set-up
-
introduce features
-
-
Begin soft rollout with 25 clients
-
meetings with directors
-
emails to practices
-
notifications to old portal users
-
Week 4
December 3-7
5 days
-
Research - Collect feedback from first rollout and share with team
-
Develop user stories and continue iterating
-
Rollout additional 25 clients
- A/B testing in full swing
- Get Data Insights involved now
End
Week 5
December 10-14
5 days
- Rollout to additional 25 clients
- Evaluate process and make changes with Implementation
- Check in with Support for ongoing themes
- Brainstorm, reevaluate, create, finalize and implement
Week 6
December 17-21
5 days
-
Rollout to final 25/100 clients
-
Plan meetings with client directors to gather insights from Account Management
Happy Holidays!!
Week 7
December 26-28
3 days
-
Expected for all 100 practices to have implemented EMR
-
Prepare for shutdown of old patient portal - send notifications/emails
-
Full shift expected by 31st
Happy New Year!
Week 8
Jan 2-4
3 days
-
Press Release announcing full launch & rollout
-
Begin Post launch Research - Collect feedback from A/B testing
-
Shut down old portal